Wires and Cables During the damage assessment phase of the Launch Platform, one of the most pervasive heat-affected elements inspectors identified was the wiring and cabling on and below the launch deck of the vessel. The team estimates that the marine segment alone requires more than nine miles and 35 different types of new cable. Cable-pulling and replacement efforts begin with the able support of Danish contractor, SEMCO Maritime.
(Sea Launch photos by |